Public Jobs

Bids due in 7 days
7/23/19 10:00 am
Knight Street Paving Improvements (Sub-Bids - Total Site Services)
Total Site Services
Richland, WA
Work to be performed includes: Sidewalk and ADA ramp improvements, HMA removal and replacement,utility relocation, pavement rehabilitation, striping and signage.
Bidding Closed
7/9/19 10:00 am
Keene Road Stormwater Improvements (Sub-Bids - Total Site Services)
Total Site Services
Richland, WA
This project includes clearing and grubbing, storm ditch excavation, placement of quarry spalls, water main relocation, storm drain pipe, manhole installation, and asphalt patching.
Bidding Closed
6/28/19 10:00 am
Wallula Dodd Water System Water Line Transmission & Distribution Mains (Sub-Bids - Total Site Serv)
Total Site Services
Walla Walla, WA
The work includes construction of approximately 435 feet of 12-inch water line, 15,850 feet of 18-inch water line, 14,095 feet of 24-inch water line, and 2,280 feet of 30-inch water line; 460 feet of 36-inch casing, 800 feet of 18-inch utility casing; 6,250 cubic yards of excavation; 4,200 cubic yards of embankment compaction; valves and fittings; combination air/vacuum valve assemblies and manholes; blow off hydrants and drainage swales; restoration work; concrete splash pads; testing; together with all other work as specified in the bidding documents. The Work may also include additive and deductive alternatives pertaining to partially restrained pipeline and the installation of approximately 10,100 feet of 2-inch PVC conduit.
Bidding Closed
6/18/19 10:00 am
Horn Rapids Landfill Disposal Capacity Improvements - Phase 1B - (Sub-Bids - Total Site Services)
Total Site Services
Richland, WA
The project area is approximately 18 acres. Generally, this requires minor excavation/embankment, grading and compacting subgrade, construction of a landfill composite geosynthetic bottom lining system, installation of HDPE leachate collection piping systems, and buried and perimeter landfill gas piping.
Bidding Closed
6/5/19 4:00 pm
W. 36th Avenue Sidewalk (Sub-Bids - Total Site Services)
Total Site Services
Kennewick, WA
The City has obtained a Washington State Transportation Improvement Board (TIB) grant to install sidewalk along the north side of W. 36th Ave. between S. Vancouver St. to 300 feet east of S. Tacoma St. or just east of S. Sharron St. The existing roadway overall width is approximately 28-feet wide. The approximate width north of the centerline is 14-feet to the edge of pavement. To accommodate for the new sidewalk, the north side will be widened an additional five (5) feet to increase the width of the roadway to 19-feet from the centerline. The improvements will include new curb, gutter, sidewalk, storm drainage and street lighting.
Bidding Closed
6/3/19 4:00 pm
Battelle Boulevard Extension (Sub-Bids - Total Site Services)
Total Site Services
Richland, WA
This project includes clearing and grubbing, roadway excavation, placement of crushed surfacing, water and sewer main lines and services, irrigation main line, new conduit and vault placement (electrical and fiber optic), new storm drain systems, street light system, surfacing with hot mix asphalt and site restoration.
Bidding Closed
5/23/19 3:00 pm
RSD Teaching, Learning & Administrative Center (Sub-Bids - Total Site Services)
Total Site Services
Richland, WA
A new 2 story building consisting of 41,000 square feet, including Site Work, Structures, Finishes, Fire Protection, Mechanical, and Electrical work.
Bidding Closed
5/8/19 4:00 pm
2019 Street Improvements (Sub-Bids - Total Site Services)
Total Site Services
Connell, WA
This project consists of three schedules. Schedule A - East Birch Street Reconstruction will reconstruct East Birch Street from Columbia Avenue to the east end of Birch Street, install new curb and gutter, sidewalk, and storm drainage. Schedule B - East Davis Street Reconstruction will pave the existing gravel road section of Davis Street from Burke Avenue to Chelan Avenue, install new curb and gutter, sidewalk, and storm drainage. Schedule C - South Columbia Avenue Sidewalk will construct a pedestrian pathway and Americans with Disabilities Act (ADA) improvements from Gum Street to the Connell Family Clinic.
Bidding Closed
5/1/19 4:00 pm
Martin Luther King School Sidewalk and Safety Improvements (Sub-Bids - Total Site Services)
Total Site Services
Union Gap, WA
The City of Union Gap invites separate sealed BIDS for the construction of the MARTIN LUTHER KING SCHOOL SIDEWALK AND SAFETY IMPROVEMENTS, State Aid No. HLP-SR17(002), HLA Project No. 17148 including the following approximate major quantities of work: SCHEDULE A Approximately 1,200 CY of unclassified excavation, 1,300 TONS crushed surfacing, 540 TONS HMA, 2,250 LF curb and gutter, 2,455 SY concrete sidewalk, storm drainage, and related improvements. SCHEDULE B Approximately 100 CY unclassified excavation, 150 TONS crushed surfacing, 55 TONS HMA and related improvements.
Bidding Closed
5/7/19 3:00 pm
Columbia River Elementary School (Sub-Bids - Total Site Services)
Total Site Services
Pasco, WA
A new 2 story building consisting of approximately 74,000 square feet, including Site Work, Structures, Finishes, Fire Protection, Mechanical, and Electrical work.